December 18, 2019

We're getting ready to wrap up another amazing year - check out our crew in shotcrete action at the Skins Spillway this fall!

July 15, 2019

We applied approximately 10,000 sqft of shotcrete at the Bridge Road Pump Station waste water treatment plant. Working in aerial lifts our crew worked to apply shotcrete to the 37' high  radius walls in tight quarters with high finish tolerances. 

November 7, 2018

This fall we installed approximately 200 cubic metres of upper crusher wet shotcrete foundation walls at Mainland Sand & Gravel in Abbotsford. Our skilled team dealt with restricted access in some areas, as well as the challenge of up to 2 metre thick shotcrete applica...

November 1, 2018

A few more shots of some shotcrete columns at UBC. We're finishing up the entry plaza soon!

October 2, 2018

We've spent a lot of time at UBC this year. Check out a few shots of our progress over the last few months

March 28, 2018

Major seismic repairs are in the works for the Alexandra Bridge located approximately 40 km North of Hope, BC. The 490 metre long bridge spans across the Fraser river, and sees a significant amount of local and tourist traffic throughout the year along Highway 1. 

...

March 25, 2018

Interior progress is moving along on the UBC Life Science Building Seismic Upgrade. We're going to be moving on to exterior work on the entry plaza soon, but for in the meantime we're finishing up installation of concrete seismic drag struts along the interior to trans...

January 31, 2018

Check out this awesome before and after of our work on the new shear walls at the west side of the UBC Life Sciences building - part of our seismic upgrade work at the Life Sciences building 2017/2018.

January 31, 2018

We've been moving forward pretty steadily at UBC. Here are some shots of a seismic beam constructed across the Life Sciences building completed back in December. Shotcrete before and after:

Please reload

Featured Posts

Beautiful BC at Skins Spillway

December 18, 2019

1/10
Please reload

Recent Posts

November 16, 2018

November 7, 2018

November 1, 2018

October 2, 2018

Please reload

Follow Us
  • Facebook Classic
  • Twitter Classic
WHAT'S UP?
Burns Lake 4.jpg

Skins Spillway Seismic Upgrade

We just finished work at the Skins Spillway seismic upgrade project in Ootsa Lake, BC

This 2 month project included chipping scaling and washing to prep the slopes, then our crew drilled anchors and grouting, finally applying two layers of steel fibre dry mix shotcrete to complete the project in late September

RECENT PROJECTS

Vancouver Post Office Building Seismic Upgrade

 

We're working on foundation walls at the massive city block sized rehabilitation project of the historic Vancouver Post Office building

Hammersly Pump Station

 

We finished work on the radius lining of Hammersly Pump Station in April. Shotcrete application was carried before and after installation of the pump screws.

RECENT POSTS

Beautiful BC at Skins Spillway

December 18, 2019

1/10
Please reload

Head Office: 17739 56A Avenue, Surrey BC V3S1G4

Tel: 604-575-2563  Fax: 604-575-3236   Lorne@LRutt.com

  • w-facebook
  • Twitter Clean
  • Facebook
  • Twitter
  • Instagram
  • LinkedIn - Black Circle